Solar Farm Connection
IndustrialProject Overview
Grid-tie interconnection for a 5MW solar farm. We engineered and installed the medium-voltage switchgear, step-up transformers, protective relaying, and SCADA monitoring system — connecting the solar array to the utility grid through a dedicated substation.
Scope of Work
- 5MW grid-tie interconnection
- Medium-voltage switchgear installation
- Step-up transformer setup
- Protective relaying & SCADA
- Utility coordination & commissioning
Results & Outcome
The solar farm now exports 5MW of clean energy to the grid, powering approximately 750 homes. Interconnection was completed 2 weeks ahead of schedule. Zero safety incidents throughout the 12-week installation.
Key Details
- Client
- Green Energy Partners
- Location
- Woodburn, OR
- Duration
- 12 weeks
- Category
- Industrial
Have a Similar Project?
Let's discuss your project. Get a free, no-obligation estimate from our licensed electricians.